00:00 Task / Tâche #4381: Cotisations 2011 2012
Due date reached, automatically increased by 3 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #3961: Revision der Wahlkampfbeiträge in Basel
Due date reached, automatically increased by 3 days. Please handle this ticket immedialty admin

06 February 2013

00:00 Task / Tâche #4480: Bericht Transparenzinitative
Due date reached, automatically increased by 3 days. Please handle this ticket immedialty admin

05 February 2013

11:30 Task / Tâche #4180: Revision durchführen
Automaticaclly enforce assigned-to to the author of the ticket admin
11:25 Task / Tâche #4180 (Done): Revision durchführen
cta
00:00 Task / Tâche #4180: Revision durchführen
Due date reached, automatically increased by 3 days. Please handle this ticket immedialty admin
11:26 Task / Tâche #3566: Eintrag der Mdb bei datareg.admin.ch
Noch bei Simon pendent cta
00:00 Task / Tâche #3566: Eintrag der Mdb bei datareg.admin.ch
Due date reached, automatically increased by 3 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #4381: Cotisations 2011 2012
Due date reached, automatically increased by 3 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #3961: Revision der Wahlkampfbeiträge in Basel
Due date reached, automatically increased by 3 days. Please handle this ticket immedialty admin

04 February 2013

15:21 Task / Tâche #3961: Revision der Wahlkampfbeiträge in Basel
s. Mail v. 04.02.2013 cta

03 February 2013

18:22 Task / Tâche #4480: Bericht Transparenzinitative
Due date reached, automatically increased by 3 days. Please handle this ticket immedialty admin

28 January 2013

21:41 Task / Tâche #4480 (Closed): Bericht Transparenzinitative
Erste Fassung des Berichts zur Transparenzinitative zur Diskussion verbreiten. Exception
14:30 Task / Tâche #4186: Strategie des Präsidiums
Automatically enforce due date for Normal Priority to 30 days in the future admin
14:19 Task / Tâche #4186 (Done): Strategie des Präsidiums
Exception
00:00 Task / Tâche #4186: Strategie des Präsidiums
Due date reached, automatically increased by 3 days. Please handle this ticket immedialty admin
14:23 Task / Tâche #3959 (Done): Routinekontroller der Zertifizierungsstelle
Exception
14:20 Task / Tâche #4171: Bericht Routinekontrolle ausarbeiten
Automatically enforce due date for Normal Priority to 30 days in the future admin
14:04 Task / Tâche #4171 (Done): Bericht Routinekontrolle ausarbeiten
Exception
14:20 Task / Tâche #4182: Followup Revision St.Gallen
Automaticaclly enforce assigned-to to the author of the ticket admin
14:14 Task / Tâche #4182 (Done): Followup Revision St.Gallen
Exception
14:20 Task / Tâche #4179: Revisionstermin festlegen
Automaticaclly enforce assigned-to to the author of the ticket admin
14:15 Task / Tâche #4179 (Done): Revisionstermin festlegen
Exception
14:11 Information / Varia #4296 (Considered): Varia: Geschäftsreglement Finanzkompetenz
Exception
14:11 Motion #4295 (Considered): Finanzantrag: Fahrkosten Revision
Genehigt durch Beschluss GPK. Exception
14:10 Task / Tâche #4177: Revisionsbericht verfassen
Automaticaclly enforce assigned-to to the author of the ticket admin
14:10 Task / Tâche #4177 (Done): Revisionsbericht verfassen
Exception
00:00 Task / Tâche #4177: Revisionsbericht verfassen
Due date reached, automatically increased by 3 days. Please handle this ticket immedialty admin
14:10 Task / Tâche #4176: Durchführung der Revision
Automaticaclly enforce assigned-to to the author of the ticket admin
14:07 Task / Tâche #4176 (Done): Durchführung der Revision
Exception
14:10 Task / Tâche #4175: Revision der PPS Buchhaltung
Automaticaclly enforce assigned-to to the author of the ticket admin
14:06 Task / Tâche #4175 (Done): Revision der PPS Buchhaltung
Exception
14:05 Motion #4172 (Considered): Bericht Routinekontrolle akzeptieren
Exception
00:00 Task / Tâche #4180: Revision durchführen
Due date reached, automatically increased by 3 days. Please handle this ticket immedialty admin

26 January 2013

00:00 Task / Tâche #4182: Followup Revision St.Gallen
Due date reached, automatically increased by 3 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #4179: Revisionstermin festlegen
Due date reached, automatically increased by 3 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #3566: Eintrag der Mdb bei datareg.admin.ch
Due date reached, automatically increased by 3 days. Please handle this ticket immedialty admin

25 January 2013

18:17 Task / Tâche #4381: Cotisations 2011 2012
Assign unassigined ticket to project leader admin
00:00 Task / Tâche #4186: Strategie des Präsidiums
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #4180: Revision durchführen
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #4177: Revisionsbericht verfassen
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin

23 January 2013

17:20 Task / Tâche #4170 (Closed): Routinekontrolle durchführen
Automatically close after 30 days admin
14:56 Task / Tâche #4381: Cotisations 2011 2012
Hello Benoît
We've seen your request and will discuss this issue in our next Mumble session.
Please have patien...
Stichflamme
13:45 Task / Tâche #4381: Cotisations 2011 2012
Je reformule notre requête, au cas où notre demande n'aurait pas été assez claire :
Le comité de la section de Fr...
Stimbard
00:00 Task / Tâche #4182: Followup Revision St.Gallen
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #4179: Revisionstermin festlegen
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #4171: Bericht Routinekontrolle ausarbeiten
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #3959: Routinekontroller der Zertifizierungsstelle
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #3566: Eintrag der Mdb bei datareg.admin.ch
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin

22 January 2013

00:00 Task / Tâche #4381: Cotisations 2011 2012
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #4186: Strategie des Präsidiums
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #4180: Revision durchführen
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #4177: Revisionsbericht verfassen
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin

21 January 2013

23:52 Motion #4295: Finanzantrag: Fahrkosten Revision
Ticket an Lukas in RL übergeben.
Derzeit beschäftigt Belegs-Software zu erstellen.
Valio

20 January 2013

00:00 Task / Tâche #4182: Followup Revision St.Gallen
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #4179: Revisionstermin festlegen
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #4171: Bericht Routinekontrolle ausarbeiten
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #3959: Routinekontroller der Zertifizierungsstelle
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #3566: Eintrag der Mdb bei datareg.admin.ch
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin

19 January 2013

00:00 Task / Tâche #4381: Cotisations 2011 2012
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #4186: Strategie des Präsidiums
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #4180: Revision durchführen
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #4177: Revisionsbericht verfassen
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin

18 January 2013

20:10 Task / Tâche #4381 (Needs Work): Cotisations 2011 2012
Automatically changed from new state after 3 days admin

17 January 2013

00:00 Task / Tâche #4182: Followup Revision St.Gallen
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #4179: Revisionstermin festlegen
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #4171: Bericht Routinekontrolle ausarbeiten
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #3959: Routinekontroller der Zertifizierungsstelle
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #3566: Eintrag der Mdb bei datareg.admin.ch
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin

16 January 2013

00:00 Task / Tâche #4186: Strategie des Präsidiums
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #4177: Revisionsbericht verfassen
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin

15 January 2013

20:05 Task / Tâche #4381 (Closed): Cotisations 2011 2012
Bonjour,
Nous avons actuellement un problème sur la rétrocession des cotisations
2011 et 2012.
Pour 2011 aucu...
Stimbard

14 January 2013

00:00 Task / Tâche #4182: Followup Revision St.Gallen
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #4179: Revisionstermin festlegen
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #4171: Bericht Routinekontrolle ausarbeiten
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #3959: Routinekontroller der Zertifizierungsstelle
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #3566: Eintrag der Mdb bei datareg.admin.ch
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin

13 January 2013

00:00 Task / Tâche #4186: Strategie des Präsidiums
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
00:00 Task / Tâche #4177: Revisionsbericht verfassen
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin

11 January 2013

22:40 Task / Tâche #4166 (Closed): Ort und Uhrzeit festlegen
Automatically close after 30 days admin
17:18 Task / Tâche #4182: Followup Revision St.Gallen
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
17:18 Task / Tâche #4180: Revision durchführen
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
17:18 Task / Tâche #4179: Revisionstermin festlegen
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
17:18 Task / Tâche #4176: Durchführung der Revision
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
17:18 Task / Tâche #4171: Bericht Routinekontrolle ausarbeiten
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
17:18 Task / Tâche #3959: Routinekontroller der Zertifizierungsstelle
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
17:18 Task / Tâche #3566: Eintrag der Mdb bei datareg.admin.ch
Due date reached, automatically increased by 2 days. Please handle this ticket immedialty admin
17:11 Task / Tâche #4109: Löschen von Mitgliederdaten - Migration von Mitgliedern
Automatically enforce due date for Normal Priority to 30 days in the future admin
17:05 Information / Varia #4296: Varia: Geschäftsreglement Finanzkompetenz
Automatically enforce due date for Normal Priority to 30 days in the future admin
17:05 Motion #4295: Finanzantrag: Fahrkosten Revision
Automatically enforce due date for Normal Priority to 30 days in the future admin
16:55 Task / Tâche #4183: Bericht erstellen
Automaticaclly enforce assigned-to to the author of the ticket admin

02 January 2013

21:52 Information / Varia #4296 (Considered): Varia: Geschäftsreglement Finanzkompetenz
Die GPK möge diskutieren, wie die Finanzkompetenz für das Budget der GPK delegiert wird. Exception
21:50 Motion #4295 (Considered): Finanzantrag: Fahrkosten Revision
Die GPK möge beschliessen, Fahrkosten für die Revision zu erstatten.
@Valio: Bitte ergänzen.
Exception

24 December 2012

17:14 Task / Tâche #4170 (Done): Routinekontrolle durchführen
Kontrolle durchgeführt am 21.12.2012. Nachkontrolle nötig, da nicht alle Unterlagen verfügbar. Exception

19 December 2012

17:54 Task / Tâche #4186 (Needs Work): Strategie des Präsidiums
Automatically changed from new state after 3 days admin
17:54 Task / Tâche #4182 (Needs Work): Followup Revision St.Gallen
Automatically changed from new state after 3 days admin
17:54 Task / Tâche #4180 (Needs Work): Revision durchführen
Automatically changed from new state after 3 days admin
17:54 Task / Tâche #4179 (Needs Work): Revisionstermin festlegen
Automatically changed from new state after 3 days admin
17:54 Task / Tâche #4177 (Needs Work): Revisionsbericht verfassen
Automatically changed from new state after 3 days admin
17:54 Task / Tâche #4176 (Needs Work): Durchführung der Revision
Automatically changed from new state after 3 days admin
17:54 Task / Tâche #4175 (Needs Work): Revision der PPS Buchhaltung
Automatically changed from new state after 3 days admin
17:54 Task / Tâche #4109 (Needs Work): Löschen von Mitgliederdaten - Migration von Mitgliedern
Automatically changed from new state after 3 days admin

13 December 2012

12:58 Task / Tâche #4183 (Done): Bericht erstellen
Längst erledigt. Siehe: http://projects.piratenpartei.ch/pad/show/526 Exception
 