Todo / A Faire #4164

closed
RE MO

Task / Tâche #3033: Liquid Feedback

LQFB: Regelwerk festlegen

Todo / A Faire #4164: LQFB: Regelwerk festlegen

Added by rettichschnidi over 13 years ago. Updated over 13 years ago.

Status:
Closed
Priority:
Normal
Assignee:
Target version:
Start date:
09 December 2012
Due date:
% Done:

100%

Estimated time:

Description

Wir sollten uns auf ein allgemeingültiges Regelwerk festlegen.

(Dies sollte ein Subticket von #3033 sein)

RE Updated by rettichschnidi over 13 years ago Actions #1

  • Parent task set to #3033

AL Updated by AlexArnold over 13 years ago Actions #2

  • Assignee set to Monzambano

AD Updated by admin over 13 years ago Actions #3

  • Due date set to 10 February 2013

Automatically enforce due date for Normal Priority to 30 days in the future

AD Updated by admin over 13 years ago Actions #4

  • Due date changed from 10 February 2013 to 13 February 2013

Due date reached, automatically increased by 3 days. Please handle this ticket immedialty

AD Updated by admin over 13 years ago Actions #5

  • Due date changed from 13 February 2013 to 16 February 2013

Due date reached, automatically increased by 3 days. Please handle this ticket immedialty

MO Updated by Monzambano over 13 years ago Actions #6

  • Status changed from Needs Work to Needs Feedback
  • % Done changed from 0 to 90

Anbei die Regelwerke. Bin gespannt auf euer Feedback!

http://projects.piratenpartei.ch/pad/edit/619

AD Updated by admin over 13 years ago Actions #7

  • Assignee changed from Monzambano to rettichschnidi

Automaticaclly enforce assigned-to to the author of the ticket

MO Updated by Monzambano over 13 years ago Actions #8

  • Assignee changed from rettichschnidi to Monzambano
  • Target version set to Vorstand 2013-02-18

AD Updated by admin over 13 years ago Actions #9

  • Assignee changed from Monzambano to rettichschnidi

Automaticaclly enforce assigned-to to the author of the ticket

AL Updated by AlexArnold over 13 years ago Actions #10

  • Tracker changed from Task / Tâche to Todo / A Faire
  • Due date deleted (16 February 2013)
  • Assignee changed from rettichschnidi to Monzambano
  • Target version deleted (Vorstand 2013-02-18)

Regelwerk kann für den Beginn so verwendet werden.

MO Updated by Monzambano over 13 years ago Actions #11

  • Target version set to Vorstand 2013-04-08

Kann imo geschlossen werden.

AL Updated by AlexArnold over 13 years ago Actions #12

  • Status changed from Needs Feedback to Needs Work

AL Updated by AlexArnold over 13 years ago Actions #13

  • Status changed from Needs Work to Done

AL Updated by AlexArnold over 13 years ago Actions #14

  • Status changed from Done to Closed
  • % Done changed from 90 to 100